PMP Scope Management — Practice Quiz
Chapter 7 · 20 questions · Rita Mulcahy style
0/0 Score
1
During project planning, a stakeholder asks the team to add a small but useful feature to the product that was not included in the approved project charter. The team believes it would take less than a day to implement. What should the project manager do?
A.Evaluate the impact of the change on all project constraints and submit a formal change request.
B.Allow the change since it is small and will not significantly impact the schedule.
C.Implement the change immediately since the stakeholder has requested it formally.
D.Reject the change because it was not part of the original project charter.
Scope Control
Show Answer
2
A project manager is reviewing completed deliverables with the customer at the end of each phase. The customer is signing off on each deliverable as it is presented. Which process is the project manager performing?
A.Control Quality
B.Validate Scope
C.Control Scope
D.Define Scope
Validate Scope
Show Answer
3
A project manager has just completed the WBS with input from the team. A team member asks why they bothered creating it since the schedule is already done. Which of the following is the BEST response?
A.The WBS ensures all deliverables are identified and serves as a basis for estimating, assigning work, and controlling scope throughout the project.
B.The WBS is required by PMI and must be created regardless of project size or type.
C.The WBS provides the schedule baseline needed for earned value measurement.
D.The WBS helps communicate project status to senior management and stakeholders.
WBS
Show Answer
4
During project execution, a team member discovers a way to add an extra feature that would significantly improve the product's user experience. The feature was not in the scope baseline and would take three days. The team member adds it without informing the project manager. This is an example of:
A.Corrective action
B.Progressive elaboration
C.Scope creep with a positive impact
D.Gold plating
Gold Plating
Show Answer
5
A project manager is developing the scope management plan. Which of the following does this plan describe?
A.The approved project scope and the list of all deliverables
B.The techniques used to elicit requirements from stakeholders
C.How scope will be planned, executed, validated, and controlled throughout the project
D.The WBS and WBS dictionary for the project
Scope Management Plan
Show Answer
6
On an agile project, the product owner has been prioritizing the backlog. Three new high-value user stories have just been identified. Adding these stories will most likely result in:
A.An increase in the project budget and timeline to accommodate the new stories
B.Reprioritization of the backlog, with lower-priority items potentially pushed to a future release
C.Automatic addition of the stories to the current iteration
D.A formal change request to the scope baseline before the stories can be added
Agile Scope
Show Answer
7
A project manager is collecting requirements for a large government project with over 200 stakeholders. Which combination of techniques would be MOST effective?
A.Questionnaires and surveys combined with facilitated workshops and targeted interviews with key stakeholders
B.Individual interviews with each of the 200 stakeholders to ensure all needs are captured
C.A single brainstorming session with all stakeholders in one meeting
D.Observation and prototyping to identify requirements without direct stakeholder involvement
Requirements Elicitation
Show Answer
8
The project scope statement has been approved. Two weeks later, a team member identifies that a previously undetected technical dependency requires adding a new deliverable. What should the project manager do FIRST?
A.Update the WBS to include the new deliverable immediately
B.Inform the sponsor and ask for additional budget
C.Assess the impact of the new deliverable on all project constraints before taking any action
D.Ask the team member to handle the dependency without adding it to the WBS
Integrated Change Control
Show Answer
9
A project manager is building a requirements traceability matrix. Which of the following BEST describes the primary purpose of this document?
A.To record who submitted each requirement and when it was approved
B.To provide a visual breakdown of all project deliverables
C.To track the status of each requirement from inception to delivery
D.To link requirements to project objectives and ensure strategic goals are achieved
Requirements Traceability
Show Answer
10
What is the difference between product scope and project scope?
A.Product scope defines who will use the product; project scope defines how it will be built.
B.Product scope refers to the features of the deliverable; project scope includes all the work needed to deliver those features, including management activities.
C.Product scope is defined by the customer; project scope is defined by the project manager.
D.Product scope and project scope are synonyms and can be used interchangeably.
Scope Definitions
Show Answer
11
A project manager is planning a software development project using an agile approach. The customer cannot fully define all product requirements upfront. Which artifact is MOST appropriate for managing product scope?
A.Product backlog prioritized by business value
B.Detailed project scope statement approved by the sponsor
C.WBS decomposed to the work package level
D.Requirements traceability matrix linking all features to business objectives
Agile Scope Artifacts
Show Answer
12
A WBS dictionary has just been created for a construction project. Which of the following is NOT typically found in a WBS dictionary?
A.Acceptance criteria for each work package
B.Resources assigned to each work package
C.The full activity sequence across the entire project (network diagram)
D.Interdependencies between work packages
WBS Dictionary
Show Answer
13
A project manager notices the team has been completing extra tasks not included in the WBS, saying these tasks improve the overall solution. The project is now running behind schedule. What is the MOST likely root cause?
A.Poor schedule estimation during planning
B.Insufficient resource allocation
C.Lack of stakeholder engagement
D.Gold plating and inadequate scope control
Scope Control
Show Answer
14
At the end of an iteration review, the product owner rejects a completed story because it does not meet the acceptance criteria. What should have been done to prevent this?
A.The project manager should have reviewed the acceptance criteria with the product owner before the iteration started.
B.The definition of done and acceptance criteria should have been clear and agreed upon before the story was built.
C.The sprint retrospective should have caught this issue before the review.
D.The product owner should have reviewed work in progress during the sprint.
Definition of Done
Show Answer
15
The scope baseline has been established. During execution, the project manager discovers that 15% of the work being performed was not included in the WBS. What should the project manager do?
A.Stop the unauthorized work, assess the full impact on all constraints, and submit a formal change request if the work is truly needed.
B.Allow the work to continue since stopping it now would cause more disruption.
C.Update the WBS immediately to include the unauthorized work.
D.Report the issue to the sponsor and wait for guidance before acting.
Scope Baseline
Show Answer
16
Two stakeholders have conflicting requirements. Engineering wants to reduce defects; operations wants to lower maintenance costs. The project manager cannot resolve the conflict. What should happen next?
A.The project manager should make a final decision and prioritize one requirement over the other.
B.Both requirements should be added to the scope as they are both legitimate.
C.The sponsor or senior management should be involved to help resolve the conflict.
D.The requirement with the greater business impact should automatically take priority.
Requirements Conflict
Show Answer
17
A project uses a hybrid approach. The infrastructure component is developed predictively; software features are delivered iteratively. Which scope tool BEST serves the infrastructure component?
A.Product backlog prioritized by the product owner
B.User stories decomposed into tasks
C.Iteration planning board with daily standups
D.WBS and WBS dictionary with a defined scope baseline
Hybrid / WBS
Show Answer
18
The team has completed the first agile release. The customer now needs an additional feature not in the original backlog. The product owner adds the story. What should happen next?
A.The feature should be added to the current iteration immediately since the customer requested it.
B.The product owner should reprioritize the backlog; the feature will be addressed based on its priority relative to other items.
C.A formal change request must be submitted to the CCB before the story can be added.
D.The customer should be informed that scope is fixed and no new features can be added.
Agile Backlog
Show Answer
19
A project manager is planning a complex IT migration. The sponsor wants requirements from legal, IT, and business teams properly captured and validated at project completion. Which document will be MOST useful?
A.Requirements traceability matrix
B.Project scope statement
C.WBS dictionary
D.Stakeholder register
Requirements Traceability
Show Answer
20
A senior developer tells the project manager: 'We have been informally working on module X for two weeks. It is not in the WBS, but the client mentioned wanting it during the kickoff meeting.' The project manager should FIRST:
A.Accept the work since it aligns with a client request and add it to the WBS retroactively.
B.Allow the team to finish module X since it is almost complete.
C.Report the issue to the sponsor as a project risk.
D.Stop the unauthorized work, assess the full impact on scope, schedule, and cost, and determine whether a formal change request is needed.
Scope Creep
Show Answer
↻ Reset Quiz
Show All Answers
Quiz Complete!
× Comment puis-je vous aider ?