PMP Schedule Management — Practice Quiz
PMP Schedule Management — Practice Quiz
Chapter 8 · 20 questions · Critical path & float included
0/0
Score
1
A project network diagram has the following paths and durations: Path 1: A→B→E = 4+6+5 = 15 weeks | Path 2: A→C→E = 4+3+5 = 12 weeks | Path 3: A→D→E = 4+9+5 = 18 weeks. What is the float of activity C?
A.0 weeks
B.3 weeks
C.6 weeks
D.9 weeks
Critical Path & Float
Show Answer
2
An activity has the following estimates: Pessimistic = 20 days, Most Likely = 12 days, Optimistic = 4 days. Using the PERT (beta) formula, what is the expected duration and the standard deviation?
A.Expected duration = 12 days, SD = 2.67 days
B.Expected duration = 12 days, SD = 2.67 days — range: 9.33 to 14.67 days
C.Expected duration = 14 days, SD = 2.67 days
D.Expected duration = 12 days, SD = 8 days
Three-Point Estimating
Show Answer
3
An activity on a non-critical path has ES=5, EF=9, LS=13, LF=17. What is the float of this activity, and what does it mean?
A.Float = 8 weeks; the activity can be delayed up to 8 weeks without delaying the project end date.
B.Float = 4 weeks; the activity is on the critical path.
C.Float = 0 weeks; the activity has no flexibility.
D.Float = 8 weeks; the activity must start no later than week 13.
Float Calculation
Show Answer
4
During execution, the project manager learns that a critical path activity will be delayed by 3 weeks due to a supplier issue. Management requests that the original end date be maintained. What should the project manager do FIRST?
A.Immediately fast track other critical path activities.
B.Crash the delayed activity by adding more resources.
C.Inform the customer that the end date cannot be met.
D.Analyze the impact on all project constraints and present options to management before taking action.
Schedule Control
Show Answer
5
The project manager wants to shorten the project duration without adding cost. Two activities on the critical path have a discretionary finish-to-start dependency. Which schedule compression technique is most appropriate?
A.Crashing, by adding resources to both activities
B.Fast tracking, by overlapping the two activities
C.Resource leveling, to optimize the schedule
D.Monte Carlo analysis, to find the optimal path
Schedule Compression
Show Answer
6
A project network has two paths: Path 1 (critical): 30 weeks | Path 2: 27 weeks. A new activity is added to Path 2, taking 6 weeks. What is the new project duration, and what happened to the critical path?
A.36 weeks; Path 1 remains the critical path
B.33 weeks; both paths are now critical
C.33 weeks; Path 2 becomes the new critical path
D.30 weeks; Path 2 still has float because of the existing buffer
Critical Path Shift
Show Answer
7
An activity has: P = 30 days, M = 18 days, O = 6 days. Using triangular distribution, what is the expected duration?
A.18 days
B.19 days
C.20 days
D.16 days
Triangular Distribution
Show Answer
8
A project manager notices that the critical path has negative float of −4 weeks. What does this mean and what should the project manager do?
A.The project is ahead of schedule by 4 weeks; no action needed.
B.The project has 4 weeks of buffer available.
C.The project will finish 4 weeks late; inform the customer and extend the deadline.
D.The planned end date is not achievable; compress the schedule or request a baseline change.
Negative Float
Show Answer
9
A project manager is deciding between fast tracking and crashing to meet a deadline. The activities in question have mandatory dependencies. Which technique is applicable?
A.Fast tracking, because it does not add cost
B.Crashing, because fast tracking requires discretionary dependencies
C.Both techniques are equally applicable regardless of dependency type
D.Neither technique; the project must be extended
Fast Track vs Crash
Show Answer
10
Two activities have the following standard deviations: Activity X = 0.5 days, Activity Y = 4.2 days. Which activity carries MORE schedule risk, and why?
A.Activity X, because a smaller standard deviation means the estimate is more conservative.
B.Activity X, because it is likely on the critical path.
C.Activity Y, because a higher standard deviation means a wider range and greater uncertainty.
D.Both activities carry equal risk since standard deviation does not indicate risk.
Standard Deviation & Risk
Show Answer
11
A project manager needs to add a contingency reserve to the schedule. Which of the following correctly describes where contingency reserves sit in relation to the schedule baseline?
A.Contingency reserves are included in the schedule baseline and are managed by the project manager.
B.Contingency reserves are not part of the schedule baseline and require change control approval to use.
C.Management reserves are included in the schedule baseline and contingency reserves are not.
D.Both contingency and management reserves are outside the schedule baseline.
Reserves
Show Answer
12
During planning, a project manager identifies that two paths in the network diagram are very close in duration: Path A = 22 weeks (critical), Path B = 21 weeks. What is the significance of this for the project?
A.The project is well managed because there is float available on Path B.
B.Path B is not a concern since it has 1 week of float.
C.The project manager should fast track Path A to create more buffer.
D.The near-critical path (Path B) creates additional risk; both paths must be closely monitored.
Near-Critical Path
Show Answer
13
An agile team has completed 3 iterations with velocities of 22, 18, and 26 story points respectively. The product backlog has 200 story points remaining. Approximately how many more iterations are needed?
A.8 iterations
B.10 iterations
C.12 iterations
D.9 iterations
Agile Velocity
Show Answer
14
A project manager wants to shorten the schedule by adding resources to a critical path activity. The additional resources will increase costs by 15%. What schedule compression technique is being used, and what is its defining characteristic?
A.Fast tracking; it reduces duration by overlapping activities
B.Resource leveling; it adjusts resource usage across the project
C.Crashing; it trades time for cost and always increases costs
D.Resource smoothing; it uses float to optimize resources without extending the schedule
Crashing
Show Answer
15
A project manager is creating estimates for a new project in an unfamiliar domain. Very little historical data is available. Which estimating technique is most appropriate for the initial high-level estimates?
A.Three-point estimating with triangular distribution, because it accounts for uncertainty when historical data is limited.
B.Parametric estimating, because it provides the most accurate results using mathematical models.
C.Bottom-up estimating, because it provides detailed estimates at the activity level.
D.Single-point estimating, because it is the fastest method available.
Estimating Techniques
Show Answer
16
Which of the following correctly describes the difference between resource leveling and resource smoothing?
A.Resource leveling uses float to adjust resources; resource smoothing extends the project duration.
B.Resource leveling may extend the project duration; resource smoothing adjusts resources only within available float.
C.Both techniques extend the project duration to accommodate resource constraints.
D.Resource smoothing extends the project duration; resource leveling does not change the schedule.
Resource Optimization
Show Answer
17
A project has the following activity data: Activity A: ES=0, EF=5, LS=0, LF=5 | Activity B: ES=5, EF=12, LS=5, LF=12 | Activity C: ES=5, EF=9, LS=8, LF=12. Which activities are on the critical path?
A.Activity A and Activity C only
B.Activity B and Activity C only
C.All three activities: A, B, and C
D.Activity A and Activity B only
Critical Path Identification
Show Answer
18
A project manager is using Monte Carlo analysis during schedule development. Which of the following BEST describes what this technique provides?
A.The exact project completion date based on the most likely estimates.
B.The critical path based on the pessimistic estimates only.
C.The probability of completing the project on or before a specific date, and the probability that any activity is on the critical path.
D.A single-point schedule baseline approved by the project sponsor.
Monte Carlo Analysis
Show Answer
19
The sponsor tells the project manager that the project must finish 4 weeks earlier than the current approved schedule. What is the project manager's BEST first response?
A.Immediately start working overtime to make up the 4 weeks.
B.Analyze the schedule to identify compression options, assess their impact on cost and risk, and present the options to the sponsor.
C.Tell the sponsor that a 4-week reduction is not feasible and request more time.
D.Fast track all activities on the critical path immediately.
Schedule Management
Show Answer
20
An activity has: ES = 10, EF = 17, LS = 14, LF = 21. The project manager adds a resource to this activity, reducing its duration from 7 to 4 days. What happens to the float of this activity?
A.Float remains 4 days because the LS and LF do not change.
B.Float increases from 4 to 6 days because the activity finishes earlier.
C.Float increases from 4 to 7 days because EF moves from 17 to 14, while LF stays at 21.
D.Float does not change because crashing only affects cost, not float.
Float & Crashing
Show Answer
↻ Reset Quiz
Show All Answers
Quiz Complete!
—