PMP Risk Management — Practice Quiz
PMP Risks & Issues Management — Practice Quiz
Chapter 12 · 20 questions · EMV, PIQQRIM & response strategies
0/0
Score
1
A project manager is proud that his team recovered quickly from a major supplier failure that delayed the project by three weeks. The sponsor congratulates the team on their resilience. What should the project manager reflect on after this situation?
A.The team demonstrated excellent crisis management skills — this is a model for future projects.
B.The recovery was fast enough; the outcome justifies the approach taken.
C.The supplier failure should have been identified as a risk during planning, with a contingency plan in place to avoid or reduce the delay.
D.The project manager should update the lessons learned register and move on.
Risk Philosophy
Show Answer
2
A project manager is reviewing risks with the team. One team member says: 'If we finish the testing phase two weeks early, we could start user training ahead of schedule and reduce overall project duration.' How should this be classified and managed?
A.This is not a risk — it is a favorable outcome and should be noted as a project success.
B.This is a positive risk (opportunity) and should be included in the risk register with a response strategy to exploit or enhance it.
C.Risks are by definition negative events; this should be tracked as a milestone, not a risk.
D.This is gold plating and should be rejected since it was not in the original plan.
Risk Definitions
Show Answer
3
A sponsor tells the project manager: 'I can accept cost overruns up to 15%, but I will not tolerate any schedule delay beyond 10 days — that is a hard limit.' Which statement BEST describes these two positions?
A.Both statements describe the sponsor's risk appetite.
B.Both statements describe the sponsor's risk threshold.
C.The first statement describes a risk threshold; the second describes risk appetite.
D.The first statement describes risk appetite (general tolerance); the second describes a risk threshold (specific point of unacceptability).
Risk Appetite vs Threshold
Show Answer
4
Which of the following correctly represents the order of the risk management processes in the Process Groups model?
A.Plan Risk Management → Identify Risks → Qualitative Analysis → Quantitative Analysis → Plan Responses → Implement Responses → Monitor Risks
B.Identify Risks → Plan Risk Management → Qualitative Analysis → Plan Responses → Quantitative Analysis → Implement Responses → Monitor Risks
C.Plan Risk Management → Quantitative Analysis → Qualitative Analysis → Identify Risks → Plan Responses → Monitor Risks → Implement Responses
D.Identify Risks → Qualitative Analysis → Quantitative Analysis → Plan Risk Management → Plan Responses → Implement Responses → Monitor Risks
Risk Processes Order
Show Answer
5
A project manager is leading a risk identification session. Two team members argue that only the core project team should be involved to keep the session focused and manageable. What is the BEST response?
A.Agree — keeping the session small ensures efficiency and avoids information overload.
B.Involve only the technical leads since they understand the risks best.
C.Risk identification should involve all stakeholders — each brings a different perspective that may uncover risks others would miss.
D.Limit participation to the project manager and the risk officer to maintain control.
Identify Risks
Show Answer
6
A project is two weeks into planning. The risk register has just been created following the Identify Risks process. A team member asks why the register does not yet show 'selected response plans' for each risk. What is the BEST explanation?
A.Selected response plans are developed during Identify Risks alongside the list of risks.
B.Selected response plans are developed during Plan Risk Responses — at this stage the register only contains potential responses, not finalized ones.
C.The team should update the risk register immediately with response plans to save time later.
D.Response plans are not part of the risk register; they belong in the project management plan.
Risk Register
Show Answer
7
A project manager evaluates a risk as 'High Probability / High Impact' using a 1-5 scale defined by the team. Another risk is evaluated as having a 72% probability of causing a $45,000 cost overrun. Which analysis does each belong to?
A.The first is qualitative analysis (subjective scale); the second is quantitative analysis (actual monetary values).
B.Both are qualitative analyses because they both involve estimation.
C.The first is quantitative; the second is qualitative because percentages are more precise.
D.Both are quantitative because they both involve numeric assessments.
Qualitative vs Quantitative
Show Answer
8
A project has the following risks: Risk A — 40% probability, $30,000 cost impact (threat). Risk B — 25% probability, $20,000 cost impact (threat). Risk C — 30% probability, $15,000 saving (opportunity). What is the total cost contingency reserve needed?
A.$16,500
B.$21,500
C.$12,500
D.$17,000
EMV Calculation
Show Answer
9
A company must decide whether to build a custom software module (cost: $80,000) or buy an off-the-shelf solution (cost: $50,000). If they build, there is a 20% chance of a $100,000 integration failure. If they buy, there is a 60% chance of a $70,000 customization cost. What is the expected total cost of each option?
A.Build: $80,000 / Buy: $50,000 — always choose the lowest base cost.
B.Build: $100,000 / Buy: $92,000 — Buy is cheaper when risk is factored in.
C.Build: $100,000 / Buy: $120,000 — Build is the better option.
D.Build: $180,000 / Buy: $120,000 — neither is acceptable.
EMV / Decision Tree
Show Answer
10
A project team identifies that a key technical resource may be reassigned to another project during a critical phase. The project manager decides to negotiate now to secure a backup resource with similar skills who can step in if needed. Which risk response strategy is being used?
A.Avoid — the threat is being eliminated before it can occur.
B.Transfer — the responsibility for the risk is being moved to another party.
C.Accept (active) — a contingency reserve is being set aside.
D.Mitigate — the impact of the threat is being reduced by ensuring a backup exists.
Response Strategies — Threats
Show Answer
11
A project manager is concerned that a complex technical component may fail during integration. She decides to add a testing phase specifically designed to eliminate the risk of failure before integration begins. Which strategy is this?
A.Avoid — the cause of the potential failure is being eliminated through additional testing.
B.Mitigate — the probability of failure is being reduced.
C.Transfer — the testing responsibility is being moved to a specialized team.
D.Exploit — the team is using the opportunity to improve the integration process.
Response Strategies — Threats
Show Answer
12
An agile team realizes there is a 40% chance they could deliver a major feature two sprints early if they bring in a more experienced developer. The project manager decides to hire the expert specifically to make sure this opportunity happens. Which strategy is being used?
A.Enhance — the probability of the opportunity occurring is being increased.
B.Exploit — specific action is being taken to ensure the opportunity occurs.
C.Share — the opportunity is being assigned to a third party.
D.Accept — the team is allowing the opportunity to occur if it naturally does.
Response Strategies — Opportunities
Show Answer
13
A project manager transfers a high-risk software development module to a specialized vendor to avoid the risk of internal team failure. During risk response planning, the team realizes there is now a risk that the vendor could go out of business. How should this new risk be classified?
A.Residual risk — it is what remains after the original risk response.
B.Pure risk — it is an insurable business risk.
C.Secondary risk — it was created by the risk response itself.
D.Transferred risk — it is now the vendor's responsibility to manage.
Secondary & Residual Risks
Show Answer
14
During execution, a previously identified risk occurs. The project manager activates the contingency plan and needs to draw from the project's reserves to fund the response. Which reserve is used and what approval is required?
A.Management reserve — the project manager can use it at their discretion.
B.Contingency reserve — the project manager can use it without external approval since it is part of the cost baseline.
C.Management reserve — sponsor approval is required before any reserve can be accessed.
D.Contingency reserve — a formal change request must be approved before it can be used.
Contingency vs Management Reserve
Show Answer
15
Three months into a project, a key piece of equipment fails unexpectedly, threatening a two-week delay. The project manager immediately calls a meeting to brainstorm solutions. A senior stakeholder asks why there was no plan in place. What does this situation indicate?
A.The project manager responded appropriately — improvised solutions are expected in project management.
B.The equipment failure should have been identified as a risk during planning, with a pre-approved contingency plan ready to activate.
C.The project manager should have purchased insurance to cover equipment failures.
D.The situation is acceptable because unknown risks cannot be anticipated.
Situational — Contingency Plan
Show Answer
16
After completing Plan Risk Responses, the project manager reviews the risk register. Which of the following would be found in the updated register at this stage?
A.Only the list of identified risks and their probability and impact ratings.
B.Quantitative analysis results and Monte Carlo simulation outputs.
C.The initial list of risks with potential (not yet selected) responses.
D.Selected response strategies, contingency plans, fallback plans, risk owners, triggers, and secondary risks.
Risk Register Updates
Show Answer
17
During project execution, the project manager holds a status meeting and reviews the risk register with the team. A risk that was on the watch list three months ago now shows signs of increasing probability. What should the project manager do?
A.Note the change in the risk register and continue monitoring.
B.Immediately escalate the risk to the sponsor for a decision.
C.Reassess the risk, update its priority ranking, and develop a response plan if it now warrants one.
D.Remove the risk from the watch list and accept it since no response was planned for it.
Monitor Risks
Show Answer
18
An agile team is planning a new product that requires integrating an untested cloud migration technology. The product owner is concerned about whether the technology will work as expected before the team begins building dependent features. What is the MOST appropriate risk management approach?
A.Accept the risk and proceed with development — if the technology fails, the team will adapt.
B.Schedule a risk spike — a short iteration dedicated to testing the technology before dependent work begins.
C.Transfer the technology risk by outsourcing the cloud migration to a vendor.
D.Add the technology risk to the backlog as a user story to be addressed in a future sprint.
Agile Risk — Spike
Show Answer
19
During risk response planning, the project manager identifies a regulatory compliance risk that could affect three other programs in the organization. The impact, if it occurs, would exceed the project's authority to resolve. What is the MOST appropriate response strategy?
A.Mitigate — reduce the probability of the compliance risk through process improvements.
B.Accept — document the risk and set aside a management reserve.
C.Escalate — the risk exceeds the project manager's authority and should be managed at the program or portfolio level.
D.Transfer — purchase regulatory compliance insurance to cover potential penalties.
Escalate Strategy
Show Answer
20
During project execution, an unexpected technical issue arises that was not identified during risk planning. The project manager organizes a working session to find an immediate solution. What is this an example of, and what does it imply about the project's risk management?
A.A workaround — an unplanned response to an unanticipated event, which suggests risk identification was incomplete.
B.A contingency plan — the project manager is activating a pre-approved response.
C.A fallback plan — the original contingency plan failed and a second-level response is being developed.
D.Risk reassessment — the project manager is re-evaluating the risk register in response to the event.
Situational — Workaround
Show Answer
↻ Reset Quiz
Show All Answers
Quiz Complete!
—