Quiz Exam PMP – Communications Management
PMP Communications Management — Practice Quiz
Chapter 11 · 20 questions · Plan, Manage & Monitor Communications
0/0
Score
1
A project manager sends weekly status reports to all stakeholders but receives frequent complaints that people are not getting the information they need. After investigating, she discovers that some stakeholders need daily updates while others prefer visual dashboards. Which process has been inadequately performed?
A.Manage Communications — the reports are not being sent correctly.
B.Plan Communications Management — stakeholder communication needs were not properly analyzed and documented.
C.Monitor Communications — the project manager failed to check whether communications were effective.
D.Integrated Change Control — stakeholder requirements should have been captured as change requests.
Communication Processes
Show Answer
2
A project starts with 6 team members. Midway through the project, 4 new members join. How many communication channels existed before, how many exist now, and what is the increase?
A.Before: 12 / After: 30 / Increase: 18
B.Before: 15 / After: 40 / Increase: 25
C.Before: 15 / After: 45 / Increase: 30
D.Before: 12 / After: 45 / Increase: 33
Communication Channels
Show Answer
3
A project manager needs to confirm that a critical technical decision has been understood by all key stakeholders before implementation begins. Which communication method is MOST appropriate?
A.Interactive communication — a meeting or call where all parties can ask questions and confirm understanding in real time.
B.Push communication — send a detailed email to all stakeholders documenting the decision.
C.Pull communication — post the decision on the project intranet so stakeholders can access it when needed.
D.Formal written communication — distribute a signed memo to all parties.
Communication Methods
Show Answer
4
A project manager is developing the communications management plan. Which of the following is MOST important to include?
A.The list of all project deliverables and their scheduled completion dates.
B.The names and contact details of all project team members.
C.The risk register and the identified communication-related risks.
D.Who needs what information, when, in what format, and through which method.
Communications Management Plan
Show Answer
5
During a project status meeting, a senior stakeholder mentions they have not received the monthly executive summary for the past two months. The project manager investigates and finds the email distribution list was incorrectly configured. Which process should have caught this issue?
A.Plan Communications Management — the distribution list should have been validated during planning.
B.Manage Communications — the project manager should have verified delivery when sending.
C.Monitor Communications — this process is specifically designed to detect communication breakdowns.
D.Stakeholder Engagement — the stakeholder should have been more proactive in requesting the reports.
Plan vs Manage vs Monitor
Show Answer
6
A project manager is preparing a report showing that the project is 10% over budget and 2 weeks behind schedule. The sponsor asks the project manager to 'soften the numbers' before presenting to the steering committee. What should the project manager do?
A.Adjust the report as requested — the sponsor has authority over how project information is presented.
B.Refuse to alter the report — project reports must be truthful, and misrepresenting performance is an ethical violation.
C.Present the accurate data to the steering committee without informing the sponsor.
D.Delay the report until the performance issues have been resolved.
Reporting
Show Answer
7
A project team holds weekly status meetings that consistently run 30 minutes over the scheduled time. Team members complain the meetings are unproductive. What is the MOST effective corrective action?
A.Cancel the weekly meetings and replace them with email status updates.
B.Extend the meeting time to accommodate all discussions.
C.Enforce meeting management practices: distribute an agenda in advance, set time limits per topic, and assign action items with deadlines.
D.Reduce meeting frequency to bi-weekly to give the team more time to prepare.
Meeting Management
Show Answer
8
A sponsor asks the project manager: 'Based on current performance, when do you think we'll actually finish, and what will it cost?' Which type of report BEST answers this question?
A.Forecasting report — it predicts future project status and performance based on current trends.
B.Status report — it describes current performance compared to the baseline.
C.Variance report — it compares actual results to baselines.
D.Earned value report — it measures cost and schedule performance.
Report Types
Show Answer
9
An agile project team wants all stakeholders, including those who don't attend daily standups, to always be able to see which features have been completed, which are in progress, and which are blocked. What is the MOST appropriate tool?
A.A weekly status report emailed to all stakeholders.
B.A project dashboard accessible via the company intranet.
C.A bi-weekly demo meeting with the product owner.
D.A Kanban board displayed prominently in the team's work area showing work status in real time.
Information Radiators
Show Answer
10
A project manager notices the team has 25 user stories in various stages of development simultaneously. Several stories have been 'in progress' for three weeks without being completed. What risk does excessive WIP create, and what is the recommended action?
A.No significant risk — having more work in progress means the team is being productive.
B.Excessive WIP hides bottlenecks, increases quality risk, and delays value delivery. The team should limit WIP and focus on finishing before starting new work.
C.The risk is primarily to the schedule. The project manager should add resources to accelerate completion.
D.The risk is budget-related. Each in-progress story represents invested money. The project manager should cut lower-priority stories.
WIP & Kanban
Show Answer
11
Two weeks before a major delivery, a technical lead informs the project manager that a critical module has a design flaw that will require significant rework. When asked why this wasn't raised earlier, the lead says: 'I was afraid of how you'd react.' What does this situation indicate, and what should the project manager do?
A.The technical lead failed to follow the communications management plan and should be formally reminded of their reporting obligations.
B.This is a scope issue — the design flaw should be addressed through the change control process.
C.The project environment is not psychologically safe. The project manager must foster an open culture where team members feel comfortable raising issues early.
D.The project manager should escalate this to HR, as the team member withheld critical project information.
Situational — Communication Breakdown
Show Answer
12
A project manager leads a hybrid project. The agile development team tracks velocity and burndown charts. The steering committee expects Gantt charts and earned value reports. A committee member complains that the agile team's communication style is 'too informal.' What is the BEST response?
A.Require the agile team to adopt traditional reporting formats for all communications going forward.
B.Explain that the same data is being tracked under both approaches, and translate agile metrics into traditional formats for the steering committee.
C.Ask the steering committee to attend daily standups so they can observe the agile team directly.
D.Separate the project into two independent workstreams to avoid communication conflicts.
Hybrid Communications
Show Answer
13
During a daily standup, a developer mentions that a dependency on a third-party API is blocking progress on two user stories. The project manager begins discussing possible solutions with the team. What should the project manager do instead?
A.Continue the discussion since the blocker directly impacts the current iteration.
B.Ask the developer to send a detailed email explaining the blocker after the meeting.
C.Escalate the blocker to the product owner immediately during the standup.
D.Note the blocker and address it after the standup — daily standups are for status reporting, not troubleshooting.
Agile Ceremonies
Show Answer
14
A team member completes a work package but does not document the approach used to solve a complex technical challenge. Another team member later spends two days solving the same problem. What quality and communication principle does this violate?
A.Knowledge sharing — critical project knowledge must be actively distributed, not siloed with individuals.
B.Control Quality — completed work packages should be inspected before closure.
C.Validate Scope — deliverables should be formally accepted before moving forward.
D.Manage Quality — the team failed to follow the approved process for documenting technical decisions.
Knowledge Sharing
Show Answer
15
A project involves stakeholders across four countries speaking three different languages, with varying levels of technical expertise. What is the MOST important factor to address in the communications management plan?
A.Standardize all communications in one language to ensure consistency.
B.Limit communications to written formats to avoid misunderstandings in verbal exchanges.
C.Tailor communication methods, language, and level of detail to each stakeholder group, accounting for cultural and linguistic differences.
D.Use technology-based communication exclusively to eliminate geographical barriers.
Communications Plan — Tailoring
Show Answer
16
An agile team has 24 story points of work in progress and an average velocity (throughput) of 30 story points per iteration. What is the cycle time, and what does a high cycle time indicate?
A.Cycle time = 0.8 iterations; this indicates the team is performing efficiently.
B.Cycle time = 0.8 iterations (or approximately 8 days in a 10-day sprint); a long cycle time indicates too much WIP, increasing quality risk.
C.Cycle time = 30/24 = 1.25; this means the team has more capacity than work.
D.Cycle time cannot be calculated without knowing the number of team members.
Cycle Time
Show Answer
17
At the end of an iteration, the agile team holds a retrospective. A team member asks: 'Why do we keep having these meetings? We're behind and we should be building, not talking.' What is the BEST response?
A.Agree — when the team is behind, retrospectives should be skipped to save time.
B.Retrospectives are quality and communication investments — they identify process improvements that prevent the same problems from recurring and save more time than they cost.
C.Schedule the retrospective for later in the project when there is more time.
D.Replace the retrospective with a written survey so the team can continue working.
Retrospective
Show Answer
18
A project manager sends a comprehensive monthly report to 15 stakeholders. Three months later, a key stakeholder says they have never understood the project's current risk status because the report 'has too much information.' What should the project manager do?
A.Reduce the report to a single page for all stakeholders to improve readability.
B.Ask the stakeholder to identify which sections they want removed.
C.Revisit the communications management plan, analyze this stakeholder's specific needs, and create a tailored summary focused on risk status.
D.Schedule a weekly call with this stakeholder to verbally review the risk section.
Situational — Feedback Loop
Show Answer
19
A project has 200 stakeholders. The project manager needs to share a large technical document (300 pages) that stakeholders can reference at their convenience, without requiring everyone to receive it immediately. Which communication method is MOST appropriate?
A.Interactive — schedule a webinar to walk all 200 stakeholders through the document.
B.Push — email the full document to all 200 stakeholders.
C.Formal written — print and distribute the document to all stakeholders.
D.Pull — post the document on the project intranet or document management system where stakeholders can access it when needed.
Push vs Pull vs Interactive
Show Answer
20
A project manager is reviewing communication effectiveness midway through a project. She finds that team members are making decisions without informing relevant stakeholders, causing rework when those stakeholders later discover and object to the decisions. What is the MOST likely root cause and corrective action?
A.The communications management plan did not clearly define who needs to be informed of which decisions. The plan should be updated and communicated to the team.
B.The team lacks discipline — each member should be reminded of their individual communication responsibilities.
C.The stakeholders are not sufficiently engaged — they should attend more project meetings.
D.This is a scope issue — decision-making authority should be formally defined in the project charter.
Monitor Communications
Show Answer
↻ Reset Quiz
Show All Answers
Quiz Complete!
—