PMP Procurement Management — Practice Quiz
PMP Procurement Management — Practice Quiz
Chapter 13 · 25 questions · Contract types, subtypes, SOW & control
0/0
Score
1
A project manager is working with an internal department to share resources for a joint initiative. They document the arrangement in a memo signed by both department heads. Later, the internal department fails to provide the agreed resources. How should the project manager address this?
A.Send a formal breach of contract notice to the department head.
B.Escalate to legal counsel since a signed document creates a binding contract.
C.Address it through internal channels — a signed memo is an agreement, not a contract, and does not carry the same legal weight.
D.File a claim through the organization's contract change control system.
Contract vs Agreement
Show Answer
2
A company is outsourcing the development of a new software system. The full scope has not yet been determined, as requirements will evolve during the project. Which contract type is MOST appropriate?
A.Cost-reimbursable, because the scope is not defined enough to establish a fixed price and the buyer will reimburse actual costs.
B.Fixed-price, because it protects the buyer from cost overruns.
C.Time and material, because it can be used for any project regardless of scope definition.
D.IDIQ, because software projects always have indefinite quantities.
Contract Type Selection
Show Answer
3
A project manager is comparing three contract options for the same procurement. Contract A is fixed-price, Contract B is time and material, Contract C is cost-reimbursable. Ranking from highest to lowest buyer cost risk, what is the correct order?
A.Fixed-price, Time and Material, Cost-reimbursable
B.Time and Material, Fixed-price, Cost-reimbursable
C.Fixed-price, Cost-reimbursable, Time and Material
D.Cost-reimbursable, Time and Material, Fixed-price
Risk and Contract Type
Show Answer
4
A buyer insists on using a fixed-price contract even though the scope of work is not yet fully defined. The seller accepts and submits a bid. Which of the following problems is MOST likely to occur during project execution?
A.The buyer will face high audit costs reviewing the seller's invoices.
B.The seller will submit frequent change orders claiming work is outside the contract, leading to disputes and cost overruns.
C.The seller will over-staff the project to ensure delivery, increasing the buyer's indirect costs.
D.The buyer will be required to reimburse all seller costs regardless of performance.
Fixed-Price Risks
Show Answer
5
A project manager needs to urgently hire two contract developers to help with a specific coding task expected to last three weeks. Which contract type is MOST appropriate, and why?
A.Cost-reimbursable, because the total effort is not precisely known.
B.Fixed-price, because the task is well-defined and will protect the buyer from overruns.
C.Time and material, because it is ideal for short-duration, staff-augmentation work that can begin quickly.
D.IDIQ, because the exact number of hours needed is indefinite.
T&M Contract
Show Answer
6
A project manager joins a project after the contract with the main vendor has already been signed. She discovers that the contract does not include reporting requirements or attendance at project meetings. What is the MOST likely consequence, and what should she have done differently?
A.Nothing — reporting is managed internally and does not need to be in the vendor contract.
B.The vendor is not obligated to attend meetings or submit reports, since these were not in the contract. The PM should have been involved before the contract was signed.
C.The PM should immediately request a verbal agreement from the vendor to cover these activities.
D.The PM should submit a change request to add these requirements to the contract retroactively.
PM Role in Procurement
Show Answer
7
Which of the following BEST describes the purpose of a procurement statement of work (SOW)?
A.To clearly and completely describe all the work the seller is required to perform, including meetings, reports, deliverables, and acceptance criteria.
B.To provide the seller with a general overview of the project so they can develop their own detailed work plan.
C.To define the buyer's internal budget for the procurement and the maximum price they are willing to pay.
D.To describe the seller's organizational structure and key personnel who will work on the project.
Procurement SOW
Show Answer
8
A company wants to understand what cloud migration services are available in the market before deciding whether to outsource. They want general information from vendors without committing to a purchase. Which document should they issue?
A.Request for Proposal (RFP) — to get detailed proposals from interested vendors.
B.Invitation for Bid (IFB) — to get pricing for the migration services.
C.Request for Information (RFI) — to collect information about available services before creating procurement documents.
D.Request for Quotation (RFQ) — to get unit pricing for specific migration tasks.
Bid Documents
Show Answer
9
During a bidder conference, a vendor asks a technical question privately to the project manager after the formal session ends. The project manager answers verbally. What is wrong with this approach?
A.Nothing — informal communication after a meeting is acceptable and common practice.
B.The project manager should only communicate with vendors through the procurement department.
C.The answer must be approved by the sponsor before being shared with any vendor.
D.All questions and answers must be documented in writing and shared with all prospective sellers to ensure fairness and equal information.
Bidder Conference
Show Answer
10
A project manager and a vendor verbally agree on the scope, schedule, and price for a consulting engagement during a phone call. No written contract is ever signed. Is this a valid contract?
A.No — only written, signed documents constitute legally valid contracts.
B.Yes — a verbal agreement can constitute a legal contract if it includes an offer, acceptance, consideration, legal capacity, and legal purpose, though it is very difficult to enforce.
C.No — contracts require approval from a procurement department to be valid.
D.Yes — verbal contracts are fully enforceable as long as both parties confirm the agreement by email.
Legal Contract Requirements
Show Answer
11
Company A has contracted Company B to build a facility. Company B subcontracts the electrical work to Company C. During a site visit, the project manager from Company A notices an issue with Company C's work and directly instructs Company C to stop and redo the work. What is the risk of this action?
A.None — the project manager has authority over all work performed on their project.
B.Company C may refuse since they only take instructions from Company A.
C.Company A may be liable for delay claims from both Company B and Company C since they have no contractual relationship with Company C.
D.The instruction is valid but must be confirmed in writing within 24 hours.
Privity
Show Answer
12
A seller fails to deliver a critical report required by the contract by the agreed deadline. The project manager is angry but decides to wait and see if the seller catches up in the next week before raising the issue. What is the risk of this approach?
A.By not immediately sending a formal written notice of breach, the buyer may lose their right to claim breach later.
B.Waiting one week is reasonable and gives the seller a chance to remedy the situation without escalation.
C.The project manager should notify the sponsor before taking any formal action.
D.There is no risk — the breach is documented in the delivery logs regardless of whether a formal notice is sent.
Breach of Contract
Show Answer
13
A construction project is significantly delayed when an unexpected earthquake damages the construction site. The seller claims force majeure and requests a schedule extension without penalty. How should this be handled?
A.The seller is in breach of contract and should pay delay penalties as specified.
B.Force majeure applies — neither party is at fault, and the seller is typically entitled to a time extension.
C.The buyer should terminate the contract and find a new seller.
D.The seller must absorb all costs since they bear the risk of loss under the fixed-price contract.
Force Majeure
Show Answer
14
During contract execution, the project manager verbally asks the seller to add a small enhancement not included in the scope of work. The seller performs the work and later invoices the buyer for the additional cost. The buyer refuses to pay, claiming the change was never formally authorized. Who is likely correct?
A.The buyer — verbal instructions from a project manager are never binding.
B.The seller — any instruction from the buyer's project manager constitutes an authorized change.
C.The seller may have a valid claim — a verbal instruction from the buyer's representative could constitute a constructive change, creating an obligation for the buyer.
D.Neither — the additional work should be removed from the invoice and the seller penalized for gold plating.
Control Procurements
Show Answer
15
A project manager needs specialized testing equipment for 8 days. The daily rental cost is $200. The purchase cost is $1,000 with a daily maintenance cost of $50. Should the project manager buy or rent the equipment?
A.Buy — the purchase cost is lower than the total rental cost.
B.Rent — rental is always more flexible and cost-effective for short durations.
C.Buy — ownership provides long-term value beyond this project.
D.Rent — the break-even point is 6.67 days; since the need is 8 days, buying becomes cheaper only beyond that point, but only marginally.
Make or Buy
Show Answer
16
A company is procuring software development services for an agile project where requirements will evolve across 12 sprints. The buyer wants to incentivize early delivery and allow payment per sprint rather than a lump sum at the end. Which contract type BEST fits this scenario?
A.Standard fixed-price contract with a penalty clause for late delivery.
B.Graduated fixed-price with fixed-price work packages for each sprint delivery.
C.Cost-reimbursable to accommodate the evolving scope.
D.Time and material to give the seller maximum flexibility.
Agile Contracts
Show Answer
17
Before signing a contract, both parties had several discussions and exchanged emails agreeing on a specific technical specification. However, the final signed contract contains different wording on that specification. Which takes precedence?
A.The pre-signing emails, since they represent the original intent of both parties.
B.Neither — a new meeting should be held to reconcile the discrepancy.
C.The signed contract supersedes all prior discussions, memos, and emails, regardless of what was agreed before signing.
D.The emails, because they are more specific than the contract language.
Contract Interpretation
Show Answer
18
A project manager works in an organization with a centralized procurement department. A vendor calls the project manager directly to discuss a change to the statement of work. What should the project manager do?
A.Refer the vendor to the procurement department and ensure all contract-related communications go through the appropriate channel.
B.Discuss the change directly with the vendor since the project manager is responsible for the scope of work.
C.Ask the vendor to submit the change request in writing and handle it independently.
D.Escalate to the sponsor before responding to the vendor.
Centralized vs Decentralized
Show Answer
19
A project manager is managing a fixed-price contract with a vendor. Midway through the project, the vendor's quality of deliverables has declined significantly, and the vendor claims they are losing money on the contract. What should the project manager watch for MOST carefully?
A.The vendor submitting excessive invoices beyond the contract price.
B.The vendor cutting scope or quality to recover their profit margin, and claiming work the buyer needs is outside the contract.
C.The vendor requesting to switch to a cost-reimbursable contract to recover their losses.
D.The vendor reassigning senior staff to more profitable projects.
Control Procurements — Fixed Price
Show Answer
20
During project execution, the project manager realizes that a deliverable specified in the contract is no longer needed due to a change in business requirements. The project manager tells the seller verbally to skip that deliverable. What is wrong with this approach, and what should be done instead?
A.Nothing — the project manager has authority to modify scope within the project.
B.The project manager should confirm the verbal instruction by email within 48 hours.
C.Any change to the contract — including removal of deliverables — must be formalized through a written contract change order, processed through integrated change control.
D.The project manager should inform the sponsor and wait for their approval before communicating with the seller.
Situational — Contract Change
Show Answer
21
A buyer signs an FPIF contract with a target cost of $500,000, a target fee of $50,000, and a sharing ratio of 80/20 (buyer/seller). The seller completes the work for $450,000 — $50,000 less than the target. What is the seller's total compensation?
A.$500,000 — the seller receives the original target cost plus the fixed fee.
B.$560,000 — the seller receives actual cost ($450,000) + target fee ($50,000) + their share of savings (20% × $50,000 = $10,000).
C.$550,000 — the seller receives the target cost plus the target fee regardless of performance.
D.$540,000 — the seller receives actual cost plus a reduced fee due to coming in under budget.
Contract Subtypes — FPIF
Show Answer
22
A project manager is reviewing a proposed contract where the seller will be reimbursed all actual costs plus a commission of 15% of those costs. What is the MAIN risk of this contract type for the buyer?
A.The seller may not have sufficient accounting systems to track actual costs accurately.
B.The buyer cannot audit the seller's invoices under this contract type.
C.The seller bears too much risk since costs could exceed the fixed percentage.
D.The seller has zero incentive to control costs — higher costs mean a higher commission, directly rewarding inefficiency.
Contract Subtypes — CPPC
Show Answer
23
A buyer is choosing between a CPIF and a CPAF contract for a complex research project. The buyer wants the seller to be motivated by objective, measurable performance targets, with the bonus amount calculated by a predetermined formula. Which contract type should be selected?
A.CPIF — the incentive fee is calculated mathematically based on objective, measurable targets defined in the contract.
B.CPAF — the award fee is based on measurable targets and provides the most objective assessment.
C.CPFF — a fixed fee ensures the seller is always motivated regardless of performance.
D.CPIF and CPAF are identical — both calculate fees based on performance metrics.
Contract Subtypes — CPIF vs CPAF
Show Answer
24
A government agency is signing a 5-year infrastructure maintenance contract. The procurement manager is concerned about the impact of inflation on material costs over such a long period. Which contract type BEST addresses this concern?
A.FPIF — the incentive fee will compensate the seller for any cost increases.
B.Cost-reimbursable — the buyer will reimburse all actual costs including inflation impacts.
C.FPEPA — the fixed price includes a clause allowing adjustment based on economic indices such as inflation rates.
D.T&M — the hourly rates can be renegotiated annually to reflect market conditions.
Contract Subtypes — FPEPA
Show Answer
25
Match each scenario to the MOST appropriate contract subtype: (1) A nonprofit organization needs consulting services but cannot pay profit to the vendor. (2) A buyer wants a fixed-price contract but needs to incentivize the vendor to finish early. (3) A buyer needs hourly developers for 3 weeks with a spending cap. (4) A construction project needs steel with pricing adjusted for commodity market fluctuations.
A.1-CPFF / 2-FPAF / 3-T&M / 4-FP
B.1-Cost Contract / 2-FPIF / 3-Not-to-Exceed T&M / 4-FPEPA
C.1-CPIF / 2-FPAF / 3-IDIQ / 4-CPFF
D.1-CPAF / 2-FPEPA / 3-T&M / 4-FPIF
Contract Subtypes — Selection
Show Answer
↻ Reset Quiz
Show All Answers
Quiz Complete!
—