PMP Quality Management — Practice Quiz
PMP Quality Management — Practice Quiz
Chapter 10 · 20 questions · Plan, Manage & Control Quality
0/0
Score
1
A software team delivers a product that includes several unrequested features the developers believed would improve user experience. The customer rejects the delivery, stating it does not meet the original requirements. Which of the following BEST explains the situation?
A.The team delivered a high-quality product that exceeded expectations.
B.The team engaged in gold plating, which violates quality principles regardless of intent.
C.The customer should accept the product since the additional features add value.
D.The project manager failed to manage stakeholder expectations effectively.
Quality Definition
Show Answer
2
A project to build a small community playground uses low-grade concrete that meets all specified strength requirements exactly. An inspector notes 'zero defects.' A senior engineer argues this is unacceptable because 'high-grade materials should always be used.' Who is correct and why?
A.The senior engineer is correct — high-grade materials always ensure better quality.
B.Both are correct — grade and quality must both be maximized on all projects.
C.The inspector is correct — the concrete is high quality because it meets the requirements, even though it is low grade.
D.Neither is correct — quality and grade are the same concept and must both be evaluated together.
Quality vs Grade
Show Answer
3
During project execution, a quality auditor visits the team and reviews whether the established installation procedures are being followed correctly by each team member. Which quality management process is being performed?
A.Manage Quality, because the audit is reviewing whether processes and procedures are being followed.
B.Control Quality, because the auditor is inspecting the work being done on the project.
C.Plan Quality Management, because the auditor is validating that the quality plan is correct.
D.Validate Scope, because the auditor is confirming that deliverables meet requirements.
Plan vs Manage vs Control Quality
Show Answer
4
At the end of a manufacturing phase, the project team measures the dimensions of produced components to determine whether they are within the acceptable tolerance range defined in the quality management plan. Which process is being performed?
A.Manage Quality, because the team is checking compliance with the quality management plan.
B.Plan Quality Management, because tolerance ranges are being validated against the plan.
C.Control Quality, because the team is inspecting deliverables to verify they meet requirements.
D.Validate Scope, because the deliverables are being reviewed for acceptance.
Plan vs Manage vs Control Quality
Show Answer
5
A project manager is categorizing quality-related costs. Training the team on installation procedures, purchasing testing equipment, reworking a defective component before delivery, and replacing a faulty product after the customer has received it — which category does each belong to respectively?
A.Appraisal, Prevention, Internal failure, External failure
B.Prevention, Internal failure, Appraisal, External failure
C.Prevention, Appraisal, External failure, Internal failure
D.Prevention, Appraisal, Internal failure, External failure
Cost of Quality
Show Answer
6
A project manager realizes that 30% of deliverables are failing quality inspections at the end of each phase. A team member suggests hiring more inspectors to catch defects faster. What should the project manager do FIRST?
A.Hire additional inspectors as suggested to improve defect detection rates.
B.Investigate the root cause of the defects and improve the processes to prevent them from occurring.
C.Increase the frequency of inspections to catch defects earlier in each phase.
D.Accept a higher defect rate as normal variation and document it in the lessons learned register.
Prevention over Inspection
Show Answer
7
A project manager is reviewing a control chart for a manufacturing process. She notices that 8 consecutive data points all fall above the mean, but none exceeds the upper control limit. What should she conclude?
A.The process is in control because all data points are within the control limits.
B.The process is performing better than expected since points are consistently above the mean.
C.The process is out of control due to the rule of seven — the non-random pattern requires investigation.
D.The upper control limit should be adjusted upward to accommodate the new performance level.
Control Charts
Show Answer
8
On a control chart, what is the difference between control limits and specification limits?
A.Control limits are the organization's internal standards for process variation; specification limits are the customer's requirements. On the exam, assume specification limits are outside the control limits.
B.Specification limits are the organization's internal standards; control limits represent the customer's requirements.
C.Control limits and specification limits are the same — both represent the acceptable range of variation.
D.Control limits are set tighter than specification limits to ensure the process always exceeds customer expectations.
Control Charts
Show Answer
9
A project manager wants to identify which defect types are causing the most quality problems on a manufacturing project. She has collected data on 12 types of defects over the past month. Which tool would BEST help her focus improvement efforts on the most impactful issues?
A.Scatter diagram, to identify correlations between defect types and their causes.
B.Pareto chart, to rank defects by frequency and identify the 20% of causes driving 80% of problems.
C.Control chart, to determine whether the defect rate is within acceptable limits.
D.Cause-and-effect diagram, to map all possible causes of each defect type.
Quality Tools
Show Answer
10
During a quality review, the team suspects that a higher paint spray quantity is causing longer drying times on a door manufacturing project. Which tool would BEST confirm or disprove this hypothesis?
A.Histogram, to show the frequency distribution of drying times.
B.Control chart, to monitor whether drying times are within acceptable limits.
C.Cause-and-effect diagram, to map all possible causes of drying time variation.
D.Scatter diagram, to determine whether there is a correlation between paint quantity and drying time.
Quality Tools
Show Answer
11
A quality department representative visits the project and reviews whether the team is using the approved testing methodology as outlined in the quality management plan. Later that day, the project manager personally reviews completed software modules to verify they have no critical bugs. Which processes are being performed respectively?
A.Control Quality, then Manage Quality.
B.Manage Quality, then Control Quality.
C.Both activities are part of Control Quality.
D.Plan Quality Management, then Control Quality.
Audit vs Inspection
Show Answer
12
A project manager notices that a repeated installation task is taking longer than planned on each iteration. She schedules a process review session after the third iteration to identify improvements that can be applied to the remaining installations. Which quality concept does this BEST represent?
A.Gold plating, because the project manager is adding work not in the original plan.
B.Control Quality, because the project manager is measuring performance against the plan.
C.Process analysis and continuous improvement, because the team is identifying improvements to an ongoing process.
D.Manage Quality, because the project manager is auditing the team's compliance with the process.
Continuous Improvement
Show Answer
13
A team member discovers that a colleague has developed a personal approach to completing a technical task that differs from the company's standard procedure. The project manager is informed. What should the project manager do FIRST?
A.Review the quality management plan to determine whether a standard process should have been followed, and address the non-compliance accordingly.
B.Thank the team member for the initiative and evaluate whether the new approach produces better results.
C.Ask the team member to document the new approach so it can be adopted across the project.
D.Report the situation to the quality department and wait for their decision.
Situational
Show Answer
14
At the end of an agile iteration, the product owner rejects a user story because it does not behave as expected. The development team argues the story matches the acceptance criteria written in the backlog. Which of the following would BEST prevent this situation in future iterations?
A.The product owner should review code in progress during the iteration to catch issues earlier.
B.The definition of done and acceptance criteria should be clearly defined and agreed upon by both the team and the product owner before the story is built.
C.The team should add more test cases to cover edge cases not in the acceptance criteria.
D.The project manager should mediate between the team and the product owner after each rejection.
Agile Quality
Show Answer
15
A project manager managing a hybrid project argues for short two-week iterations for the software component. A stakeholder asks why not do quarterly reviews instead, since that is how the organization traditionally operates. What is the BEST justification for short iterations?
A.Short iterations generate more status reports, improving stakeholder visibility.
B.Short iterations allow the team to deliver features faster and bill the client more frequently.
C.Short iterations allow quality issues to be identified and corrected earlier, when the cost of change is lowest.
D.Short iterations are required by the Scrum framework and cannot be modified.
Cost of Change
Show Answer
16
A project is manufacturing 10,000 identical components. Inspecting every component would take three weeks and delay the project significantly. The quality manager proposes inspecting a statistically valid sample. Which statement about statistical sampling is MOST accurate for the exam?
A.Statistical sampling is only acceptable when the full population cannot be inspected due to time constraints.
B.Statistical sampling reduces the reliability of quality control and should be avoided when possible.
C.Statistical sampling is most useful when the defect rate is expected to be high.
D.Statistical sampling is appropriate when inspection of the full population would take too long, cost too much, or be destructive. Sample size is determined during planning.
Statistical Sampling
Show Answer
17
A project manager is developing the quality management plan for a complex construction project. Which of the following is MOST important to include in this plan?
A.The quality metrics, control thresholds, roles and responsibilities, and processes for continuous improvement.
B.The list of all deliverables and their scheduled completion dates.
C.The names of all team members responsible for producing deliverables.
D.The customer's satisfaction score targets for the end of the project.
Quality Management Plan
Show Answer
18
Two weeks before a major delivery, the project manager receives Control Quality measurement results showing that a key deliverable is slightly outside the specification limits but within the control limits. What should the project manager do?
A.Accept the deliverable since it is within the control limits and therefore in statistical control.
B.Escalate the issue — being outside specification limits means the customer's requirements are not met, regardless of control limits.
C.Update the specification limits to align with the current performance level.
D.Notify the quality department and wait for their assessment before taking action.
Situational
Show Answer
19
A project has experienced recurring software defects in the same module across three consecutive iterations. The project manager wants to prevent recurrence. Which approach is MOST appropriate?
A.Increase the frequency of inspections on that module in future iterations.
B.Add a dedicated tester to the team to catch defects faster.
C.Conduct a root cause analysis using a cause-and-effect diagram to identify and address the underlying process issue.
D.Accept the defects as part of the normal development process and monitor their frequency.
Root Cause Analysis
Show Answer
20
During a quality audit, it is discovered that the project team has not been using the organization's approved risk assessment template when reviewing new risks. The quality auditor notes this as a compliance gap. What is the MOST appropriate action for the project manager?
A.Dismiss the finding since risk management and quality management are separate processes.
B.Implement corrective action by ensuring the team uses the approved template going forward, and investigate whether past risk assessments need to be redone.
C.Request a change to the quality management plan to remove the requirement for the approved template.
D.Inform the sponsor of the gap and wait for their instructions before taking action.
Manage Quality
Show Answer
↻ Reset Quiz
Show All Answers